The first element of the Fehmarnbelt tunnel successfully immersed

After a multi-day operation, the first of a total of 89 concrete elements for the Fehmarnbelt tunnel is now in place on the seabed. The historic event began late on Monday evening, 4 May 2026. Five tugboats and the special immersion vessel IVY transported the tunnel element from the tunnel factory at Rødbyhavn on the Danish island of Lolland to the immersion point off the Danish coast.

Around noon on Wednesday, the immersion itself began. Approximately 14 hours later, the dedicated position in the Fehmarnbelt had been reached, and the first tunnel element had been positioned precisely in the tunnel trench in front of the Danish tunnel portal. Subsequently, the element was connected to the portal using hydraulic arms. The position was then finally confirmed by precise laser measurements inside the immersed tunnel element. Later in the day, IVY will then be released from the element. 

Read full announcement (external link)

Originally published on 7 May

Read More

First tunnel element of the Fehmarnbelt tunnel to be immersed

The first of the 89 concrete elements that will make up the future Fehmarnbelt tunnel between Denmark and Germany is now on its way to the immersion point off the coast near Rødbyhavn on the Danish island of Lolland.

The 217-metre-long and 73,500-tonne concrete element left the work harbour of the tunnel factory at 9 pm on 4 May 2026. In preparation of the immersion, the contractors added a further 4,500 tonnes of ballast concrete to ensure the element is heavy enough to sink to the seabed. Now the just over two-kilometre journey to the immersion point off the future tunnel portal has just begun.

Read full announcement (external link)

Originally published on 4 May

Read More

First tunnel element prepared for immersion

Preparation of the first element for the Fehmarnbelt tunnel is well under way. The element, which is the first of a total of 89, has just been filled with 4,500 tonnes of ballast concrete. This increases the weight from 73,500 tonnes and enables the element to later sink in a controlled manner down onto the seabed.

The work inside the element has been carried out via a temporary access structure consisting of five shafts, which are bolted onto the watertight steel bulkheads that keep the water out. At one end there is a materials lift, a concrete shaft and a man‑access shaft, which also functions as ventilation. At the other end there is a ventilation shaft and an emergency shaft for personnel.

Read full announcement (external link)

Originally published on 22 Apr

Read More

Immersion pontoon IVY passes final test and receives approval

The immersion pontoon IVY has passed its final tests and is now approved by the Danish Maritime Authority. Therefore, the contractor Femern Link Contractors (FLC) can begin preparing to immerse the first tunnel element into the dredged tunnel trench off Lolland’s coast this spring.

The special vessel IVY is comprised of two distinct units: IVY 1 & 2. Prior to the transportation and immersion of a 217-metre-long standard tunnel element, each end is securely attached to IVY 1 & 2, which provide buoyancy. For the handling of the 39-metre-long special elements, IVY 1 & 2 are joined to form a single vessel, facilitating the immersion process. Together, IVY 1 & 2 are equipped with 23 kilometres of steel wire spread over 66 winches, enabling them to submerge tunnel elements to depths of up to 40 metres with exceptional precision.

Read full announcement (external link)

Originally published on 3 Apr

Read More

Contractor tests special vessel for immersion of tunnel elements

At present, the contractor consortium Femern Link Contractors (FLC) is testing the special vessel that will immerse the tunnel elements for the Fehmarnbelt tunnel. Over the weekend, the unique immersion pontoon IVY 1 & 2 carried out the first test of connecting the vessel to a completed tunnel element.

The immersion pontoons are currently located in the large Danish work harbour on Lolland, with the first tunnel element secured between the two units. The initial phase of testing has already been successfully completed and includes, among other things, confirming that all functions operate correctly – both when IVY 1 & 2 are operated separately holding a standard element secured in between, and when they are operated as a combined vessel.

Read full announcement (external link)

Originally published on 3 Mar

Read More

A new special vessel at the Fehmarnbelt project

A new special vessel has arrived in the work harbour in Rødbyhavn. It is the large floating crane “Hebo Lift 9”. The floating crane will place the enormous anchors on the seabed, to which the immersion pontoon IVY will be attached with long steel wires in connection with the immersion of the first tunnel element this spring.

A total of eight anchors weighing 500 tonnes each will be used. The anchors are shaped like large boxes and are lowered onto the seabed. After the immersion of an element, the anchors can then be picked up again by the crane and reused in connection with the immersion of the next element.

Read full announcement (external link)

Originally published on 30 Jan

Read More

Preparations underway for immersing tunnel elements into the Fehmarnbelt

Preparations for the special vessel IVY, which will play a key role in the construction of the Fehmarnbelt tunnel, are nearing completion. The approval of the immersion pontoon is almost two years behind the original schedule.

In the coming weeks, the first part of the tunnel trench will be prepared for immersion. The trench is being adapted to the elements, and the contractor is laying a gravel bed to create an even base for the tunnel elements.

Read full announcement (external link)

Originally published on 21 Jan

Read More